Quoting 12% below? Find where the job stops paying first

By CA Karan Gupta

accounting
4/11/2026
Quoting 12% below? Find where the job stops paying first featured image

A works contractor who quotes below the estimate on gross margin alone treats every statutory deduction as either free or lost, and both are wrong: on a ₹1 crore estimate where his cost and overhead

Summary

A works contractor who quotes below the estimate on gross margin alone treats every statutory deduction as either free or lost, and both are wrong: on a ₹1 crore estimate where his cost and overhead come to 81%, the job stops paying at about 17.3% below, not the 19% the margin suggests, and at 12% below about ₹5.7 lakh of his money is held back for over a year. The decision that fixes the quote is to sort each deduction into cost or delay, then solve for the break-even.

The situation

The night before a PWD bid closes, a contractor and his accountant do the sum every contractor does. Estimate ₹1 crore. Cost to do the work, about ₹76 lakh. Head-office overhead, about ₹5 lakh. So the job pays down to 19% below, and 12% below leaves ₹7 lakh.

Then the first running bill is paid, and ₹6.6 lakh of an ₹88 lakh bill never reaches the bank.

Some of that ₹6.6 lakh is gone. Most of it is only somewhere else: in the GST cash ledger, in the income-tax credit, with the department until the defect liability period ends. A bid sheet that does not separate the two gets both the price and the cash plan wrong, in opposite directions.

The rule, in one table

On the ₹88 lakh contract (12% below a ₹1 crore estimate), per bill:

DeductionAmountCost or delay?Comes back
Labour cess, 1% (BOCW Cess Act, 1996)₹88,000CostNever
GST TDS, 2% (section 51, CGST Act)₹1,76,000DelayCash ledger after the department files GSTR-7; usable only against GST
Income-tax TDS, 2% (section 393(1), Table Sl. No. 6(i) of the Income-tax Act, 2025, the old section 194C)₹1,76,000DelayCredit against the year's tax
Security deposit, 2.5% of each bill (CPWD conditions)₹2,20,000DelayAfter the defect liability period
Performance guarantee, 5% (CPWD conditions)Not deductedBank commission is a costReleased after completion
Royalty above the assessed figureNil hereDelayWith the mining clearance certificate

GST itself is neither. Works contracts are 18% since 22 September 2025, the department pays it, and section 17(5)(c) of the CGST Act leaves a works contractor his input credit. Its only cost is the weeks between paying output tax and being paid.

Where people go wrong

Pricing the deductions as zero. The gross-margin sum ignores the ₹88,000 of cess, which is lost, and the ₹93,207 it costs to finance the money held back (guarantee commission about ₹7,700, interest on the locked ₹5.72 lakh about ₹71,000, the GST lag about ₹14,500). That ₹1.81 lakh is why ₹7 lakh becomes ₹5.19 lakh, and why break-even is 17.3% below, not 19%.

Pricing the deductions as lost. The opposite habit, and just as common: a contractor who adds 2% GST TDS and 2% income-tax TDS to his costs quotes four points too high and loses bids he could have won. Tax deducted is a credit. Only its time costs money.

Forgetting royalty. If the work consumes minor minerals with royalty assessed at ₹4 lakh and the division withholds five times that until the clearance certificate, the same job's break-even falls to about 12.3% below. At 12% below it barely pays at all.

Forgetting how long the deposit is gone. The 2.5% held from every running bill does not come back when the work is finished; it comes back after the defect liability period. On a twelve-month job with a twelve-month liability period, the first bill's deposit is away for about two years at your overdraft rate. A longer liability period in the NIT moves the break-even on its own, before anything else changes.

Using the rate as the plan. Every point below costs about ₹98,000 on this job. The break-even is the one number worth knowing before choosing a quote, and it moves with the security deposit, the defect liability period and your cost of funds.

What to do

  1. Replace the 76% with your own rate analysis. It is the number that moves the answer most.
  2. Read the NIT for the security deposit, performance guarantee, defect liability period and any mobilisation advance. They are contract terms, not statute, and departments differ.
  3. Mark each deduction as cost or delay, and price the delay at your real cost of funds.
  4. Solve for the break-even before you choose a quote, then decide how close to it the competition forces you.
  5. Before bidding, check the bid-capacity clause clears: Open the bid capacity page

The tool

I built this because the night-before-the-bid sum kept coming to my desk with the same two errors. You type the estimate, your cost as a percentage of it, the quote, the security deposit and any royalty; it shows what reaches the bank per ₹100 of tender value, how much is locked and for about how long, the profit, and the percentage below the estimate at which the job stops paying, and moves them live as you change the quote, then prints a one-page working paper for your own file. It labels its three assumptions (the 76% cost, 11% cost of funds, 1.5% guarantee commission) and the contested cess base. It does not do a rate analysis, read the NIT or test bid capacity, it does not model a GeM manpower bid, and it will not tell you what to quote. Nothing is uploaded. Use it free, and verify with your CA.

Open the tender bid viability page

Sources

  1. CBIC — section 51, CGST Act, 2017 — https://taxinformation.cbic.gov.in/content/html/tax_repository/gst/acts/2017_CGST_act/active/chapter10/section51_v1.00.html
  2. Indian Kanoon — section 3, BOCW Welfare Cess Act, 1996 — https://indiankanoon.org/doc/1902664/
  3. Indian Kanoon — section 17(5), CGST Act, 2017 — https://indiankanoon.org/doc/134183062/
  4. TDSMAN — TDS on payments to contractors, section 393(1) (section 194C) (June 2026) — https://blog.tdsman.com/2026/06/tds-on-payments-to-contractors-section-3931-section-194c/
  5. GFR 2017, Rule 171 (performance security) — https://constitutionofindia.in/rule-171-of-the-general-financial-rules-2017-performance-security/
  6. CPWD General Conditions of Contract, 2019 — https://www.niperhyd.ac.in/Tenders/CPWD_GCC.pdf
  7. TaxGuru — GST rates from 22 September 2025, topic-wise — https://taxguru.in/goods-and-service-tax/gst-rate-w-e-f-22nd-september-2025-topic-wise-analysis.html
  8. TaxGuru — GST and royalty deductions in government contracts (24 January 2026) — https://taxguru.in/goods-and-service-tax/gst-royalty-deductions-government-contracts.html