Bid capacity: one contractor, four answers from one clause
Assessed available bid capacity is (A × N × M) − B, and a CA certifying it for a works tender has to apply the clause as printed in that NIT, because the multiplier, the updating of A, the period B
Summary
Assessed available bid capacity is (A × N × M) − B, and a CA certifying it for a works tender has to apply the clause as printed in that NIT, because the multiplier, the updating of A, the period B covers and even N differ between departments. On the same contractor's books the same ₹95 crore tender can clear by ₹47 crore or fail by ₹10 crore depending on those choices, so the certificate must say which reading it applied, and carry a UDIN generated within 60 days of signing.
The situation
A contractor client needs a bid-capacity certificate by Friday for a ₹95 crore road tender. He sends his best year's figure (₹32 crore in FY 2023-24), his order book (₹35 crore still to execute, ₹18 crore of it in the next twelve months) and a note that the work is to be completed in two years. He wants one line: "capacity ₹X crore".
A bid that fails the bid-capacity clause is rejected at the technical stage, after the earnest money and tender fee are spent. The arithmetic is trivial. What rejects otherwise eligible bidders is which arithmetic.
The rule
The classic clause, reproduced across Indian works tenders, reads: assessed available bid capacity = (A × N × 2) − B, where
- A is the maximum value of works executed in any one year during the last five years, updated to the current price level;
- N is the number of years prescribed for completion of the work being tendered;
- B is the value, at current price level, of existing commitments and ongoing works to be completed during the next one year.
Three parts of that sentence vary in the field:
The multiplier. ×2 is the common MoRTH / CPWD-style figure. ×1.5 is in commercial use, and ×2.5 appears in some NITs. There is no default in law.
Updating A. The classic clause allows 10% a year. The MoRTH / NHAI wording brings executed works to current cost at 7% a year, simple, from completion to the day before the last date of bid submission. Both are simple, not compound, and both run to the bid date, not to a financial year end. Some NITs give a cost index; some allow no updating.
B's period. The classic clause says the next one year. Other published versions of the same formula use the balance of the order book over the next N years.
And N is not always the completion period. Two West Bengal PWD annexures fix it in the tender itself, one at 1.5 years and another at 3 years, whatever the contract period. For a joint venture the clause applies capacity partner by partner, to the extent of each partner's participation.
Here is what that does to the client above (bid date 30 September 2026, updating from 31 March 2024):
| Reading applied | Capacity | Against ₹95 crore |
|---|---|---|
| ×2, no updating, B over the whole period (₹35 cr) | ₹93.00 cr | Fails by ₹2.00 cr |
| ×2, A updated at 10% simple, B whole period | ₹124.98 cr | Clears by ₹29.98 cr |
| ×1.5, A updated at 10% simple, B whole period | ₹84.99 cr | Fails by ₹10.01 cr |
| ×2, A updated at 10% simple, B next one year (₹18 cr) | ₹141.98 cr | Clears by ₹46.98 cr |
Same books, same tender, two passes and two failures.
The certificate. ICAI's Guidance Note on Reports or Certificates for Special Purposes (Revised 2016) governs its shape: title, addressee, the subject matter and the criteria it is measured against (here, the NIT's clause), management's responsibility, the practitioner's responsibility, the procedures performed, the conclusion, a restriction on use, and signature with membership and firm registration numbers. A UDIN is mandatory; ICAI's Council extended the generation window from 15 to 60 days from the date of signing in September 2021, and the portal has run on ICAI's DigiCA platform since 20 December 2025.
Where people go wrong
Certifying turnover as A. The clause says works executed. Trading income, other business receipts and anything in the profit and loss account that is not works are out. At least one firm selling this certificate online describes A as "maximum annual turnover". That is the commonest way A is overstated, and the first thing a rival bidder's challenge looks at.
Skipping the updating the NIT allows. In the table, leaving A at its historical figure turns a ₹29.98 crore surplus into a ₹2 crore shortfall. If the clause permits updating, a certificate without it can cost the client the bid.
Updating the wrong way. Compounding, or escalating to 31 March, or starting from the first day of the best year, all overstate or understate A against a clause that says simple and says the bid date. For an annual figure the clause's start point ("the date of completion") is not self-evident; state the one you used.
Taking B from the client's summary. Next one year and next N years can differ by half the order book. Read the NIT, and certify the definition it prints.
Using the completion period for N when the tender fixes N. The WB PWD annexures are the clearest examples; others exist.
A certificate that says only the number. Without the clause, the updating rate, B's definition and the documents examined, the figure cannot be checked, and a certificate that cannot be checked invites a challenge. It also should not say anything about turnover, similar work, net worth or bid security unless you examined those too.
What to do
- Get the NIT's bid-capacity clause in writing and read four things off it: the multiplier, the updating rule, B's period and how N is fixed.
- Build A from works executed, year by year for five years, from the books and completion certificates, and update the best year exactly as the clause says, to the day before the bid date.
- Take B from the work orders and the client's own schedule of works in hand, for the period the clause names.
- Draft the certificate with the clause, the method and the documents examined, and restrict its use to this tender.
- Sign, then generate the UDIN within 60 days, and never print a placeholder where it goes.
The tool
I sign these for contractor clients at every bid deadline, and each NIT reads the formula a little differently, so I built a page for it. You enter the five figures and pick the clause from a named list (MoRTH/CPWD-style, NHAI-style 7%, the WB PWD fixed-N variants, or your own four parameters); it gives the verdict against the tender value, shows the other readings of B and the multiplier beside yours, applies a joint-venture share, and prints the certificate on your letterhead with the computation, the definition applied, a documents-examined paragraph and a restriction on use. It does not read the NIT, does not check the other eligibility limbs, does not verify the client's figures and does not generate or remember a UDIN (a blank one prints as a blank line). The certificate text is a starting draft built from settled practice, so read it against the Guidance Note before you sign. Nothing is uploaded. Use it free.
Sources
- Law Insider — bid capacity clause (the classic formula, 10% a year, B over the next one year, joint ventures) — https://www.lawinsider.com/clause/bid-capacity/_5
- MoRTH — procedure for invitation of tender and qualification of contractors (27 November 2009) — https://morth.nic.in/sites/default/files/circulars_document/T-2009.11.27-Procedure%20for%20invitation%20of%20tender%20and%20qualification%20of%20contractors-modification%20in%20procedure.pdf
- NHAI — RFP (2021), 7% simple updating — https://nhai.gov.in/nhai/sites/default/files/mix_file/RFP_2021.pdf
- InfraLens — available bid capacity formula (B over N years; multipliers in use) — https://tenders.infralens.in/resources/available-bid-capacity-formula
- West Bengal PWD — NIT annexures on the calculation of bid capacity — https://wbpwd.gov.in
- ICAI — aligning the UDIN generation time limit from 15 to 60 days — https://www.icai.org/post/aligning-the-time-limit-of-generating-udin-from-15days-to-60days
- ICAI — Guidance Note on Reports or Certificates for Special Purposes (Revised 2016) — https://caalley.com/gn/43452aasb-gn-rcsp.pdf
- Ardhorajiya & Co — bid capacity certificate by CA (the "maximum annual turnover" description) — https://ardhorajiya.com/bid-capacity-certificate-by-ca/